ROADMAP

According to the project plan, the
following works have to be currently
performed in three stages:

New prototypes

Manufacturing five sets of DAE pilot
and experimental prototypes
9 – 12 months

Prototypes testing

Arranging pilot works on DAE use at
il and gas fields and adjusting the
new technology of hydrocarbons
production
2 – 3 months

Refinement

Finalizing WDD (working design
documentation) to issue equipment
small-lot batches

- Issuing process documentation on
DAE use at GOF

- Obtaining field-specific certificates and
licenses for new technology and equipment use
9 – 12 months

Project implementation deadlines – 15-17 months

Implementation stages and deadlines

Intended tasks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Arranging funding
3 months
Manufacturing the special geophysical cable
5 months
Manufacturing the acoustic emitter
8 months
Manufacturing the above-ground power supply generator
8 months
Manufacturing the all-climate automatic plant
4 months
Manufacturing the hoisting plant
4 months
Manufacturing the instrumentation and control equipment
6 months
Arranging pilot works on DAE use at oil and gas fields and adjusting the new technology of hydrocarbons production
4 months
Finalizing WDD to issue equipment small-lot batches up to 100 pcs. per year
2 months
Issuing process documentation on DAE use at GOF
2 months
Obtaining field-specific certificates and licenses for new technology and equipment use
2 months

IMPORTANT!

We have also begun to prepare an industrial production plan in cooperation with our partners.